During the work and sign-off

The short answer

A New York City renovation is not finished when the contractor leaves. Once every permit is signed off, the owner asks the Department of Buildings for a Letter of Completion, and the final payment should be held until then. Along the way, older buildings trigger lead rules (built before 1978) and an asbestos assessment (built before April 1987), and occupied buildings need a Tenant Protection Plan.

Proven Pros · rules checked November 2026 · permit data to Aug 2026

Lead safe work rules

Pre-1978

Housing built before then

Asbestos assessment

Pre-1987

Buildings from before April 1987

Notice before work

72 hours

When a Tenant Protection Plan applies

Once work starts your job is to keep it legal, keep changes on paper, and make sure it is formally closed at the end.

Old buildings: lead and asbestos

  • Lead paint. The city's lead safe work practices cover housing built before 1978. They apply to work that disturbs more than a small area of paint or removes windows, and the firm doing it must be certified by the federal Environmental Protection Agency.
  • Asbestos. For buildings that predate April 1987, a certified asbestos investigator has to assess the work area before the Buildings Department will issue a permit. If the work will not disturb asbestos, the investigator files a form called an ACP-5.

Ask your contractor who is handling each of these and ask to see the paperwork.

If neighbors live in the building

Permitted construction in a building with at least one occupied apartment needs a Tenant Protection Plan, and the Buildings Department must be notified 72 hours before work starts. It covers dust, noise, exits and essential services.

Changes

Something will change once the walls are open. Each change should be a written, signed change order with a price before the work is done. See step 7.

Closing the job

A permit is not finished when the contractor leaves. For work that does not change the Certificate of Occupancy, the owner or the applicant asks the Buildings Department for a Letter of Completion once every permit on the job has been signed off.

  • Hold the final payment until the sign-offs are done. That is the Attorney General's advice, and it is the only real leverage you have.
  • Look your address up afterward in both the DOB NOW public portal and the Buildings Information System, and confirm nothing is left open.

An open permit or violation stays with the property. In the Buildings Department's words, open violations "can prevent an owner from selling or refinancing."

You are done

Keep the contract, the permits, the sign-offs and the final invoice together. The next buyer's lawyer will ask for them.

Questions people ask

What is a Letter of Completion?

It is what the Department of Buildings issues to close out an alteration that does not need a new Certificate of Occupancy. The owner or applicant requests it once every permit on the job has been signed off.

When should I make the final payment to my contractor?

After the job is complete, inspections are done and the sign-offs are final. That is the New York Attorney General's advice.

Why do open permits matter when selling?

Open permits and violations stay with the property. The Department of Buildings says open violations can prevent an owner from selling or refinancing.

Do I need an asbestos inspection to renovate in NYC?

For buildings from before April 1987, a certified asbestos investigator must assess the work area before the Department of Buildings will issue a permit.

Where this comes from

To cite this page: Proven Pros, "During the work and sign-off," Renovating in New York City, provenpros.co/renovate/during-and-sign-off/. Cost figures are Proven Pros' analysis of 132,268 NYC Department of Buildings filings, records as of Aug 2026. Rules were checked against the sources above in November 2026. This guide is general information, not legal advice. Rules and fees change, so confirm with the agency and your building before you start.