In a house you answer to the city. In an apartment you answer to the building first, and in a landmarked building to a third body as well. None of these are quick, so start them before you sign with a contractor.
Co-ops and condos: the alteration agreement
Almost every co-op and most condos require you to sign an alteration agreement before work begins. There is no single city rule here. Your building's own document decides, so ask the managing agent for it first. What follows is typical practice, as reported by New York real estate publications.
- Your plans are reviewed by the building's architect or engineer, at your expense.
- Your contractor must carry insurance at the level the building sets.
- You may pay a deposit that is returned when the work is finished without damage.
- The building sets the working days and hours, and often a deadline with penalties for running over.
- "Wet over dry" is usually restricted. Many buildings will not let you put a bathroom or kitchen above a neighbor's living room or bedroom. This is a building rule, not a city one.
Published estimates for board approval range from a few weeks to about three months. Ask your managing agent how long recent approvals in your building have taken.
Landmarks
If your building is an individual landmark or sits in a historic district, the Landmarks Preservation Commission must approve the work before the Buildings Department will issue a permit. The commission says interior work needs its approval when the work requires a Buildings permit, affects the exterior (vents and louvers count), or touches a designated interior.
| Approval | For | How long |
|---|---|---|
| Certificate of No Effect | Interior renovations that need a Buildings permit and do not affect protected features | Often about 10 business days for a complete application; the commission's deadline is 30 |
| Permit for Minor Work | Exterior work that needs no Buildings permit, such as replacing windows in existing openings | Deadline of 20 business days |
| Certificate of Appropriateness | Additions, demolition and other work that changes protected features | A public hearing; about three months |
Ask the contractor
Have they worked in a building like yours? A contractor's page here shows the boroughs they file in and, for some, landmark and brownstone work. Check a contractor.
Questions people ask
What is an alteration agreement?
It is the contract between you and your co-op or condo that governs a renovation. It lets the building review your plans and sets rules on insurance, deposits, working hours and deadlines. Each building writes its own.
How long does co-op board approval take for a renovation?
Published estimates range from a few weeks to about three months. It depends on the building, so ask your managing agent how long recent approvals took.
Do I need Landmarks approval for interior work?
Yes, when the interior work needs a Department of Buildings permit, affects the exterior, or touches a designated interior. Most interior renovations get a Certificate of No Effect.
What does "wet over dry" mean?
It is a building rule, not a city law, that stops you putting a kitchen or bathroom above a neighbor's bedroom or living room.