Install construction fencing around entire site to include construction entrances/gates. Interrupting travel lanes and parking along 10th Street and N. Irving. Parking Meter IR01000N to be removed.; Work in ROW; Transportation ROW - no excavationArlington County · 2026
Asphalt paving of 20th St. and N Moore St. for new construction related to J. Rivelle (1950 Lynn St.).; Work in ROW; Transportation ROW - no excavationArlington County · 2026
600 N Glebe Project Phase 2 - Sheeting and Shoring ONLY; Amendment; Commercial New - Revision to ApprovedArlington County · 2025$860,000
2,000 to 2,499 square feet; NA; DemolitionArlington County · 2025
Installation of new dry utility cross at SW corner of 19th St. and N Moore.; NA; Transportation ROW - with excavationArlington County · 2025
Crystal House 3 - Excavation/Sheeting/Shoring; Amendment; Commercial New - Revision to ApprovedArlington County · 2025$1,900,000
Installation of new curb and gutter along N Lynn St. in association with new construction at 1901 N Moore; NA; Transportation ROW - with excavationArlington County · 2025
This profile was built from public permit records. Claim it free to add your photo, phone, and website, so the homeowners landing here can actually reach you.
Track record sourced from public building-permit records. Figures reflect permitted projects, not self-reported work. Listed on Proven Pros.
RENOVATION OF AN EXISTING BELOW GRADE PARKING STRUCTURE. NEW GARAGE SLAB ON GRADE AND NEW SECOND FLOOR PARTIALLY ELEVATED FLOOR LEVEL. THE SECOND FLOOR SLAB IS 4" BELOW THE AVERAGE SITE ELEVATION AND PREDOMINATELY (67%) BELOW GRADE OR SLAB ON GRADE. THIS WORK IS TO PREPARE FOR NEW APARTMENT BUILDING - CNEW24-02089; New; Commercial NewArlington County · 2025$20,000,000
MIXED-USE BUILDING WITH RETAIL SPACES AT GROUND LEVEL, TWO BELOW-GRADE GARAGE LEVELS, TWO ABOVE-GRADE GARAGE LEVELS AND RESIDENTIAL RENTAL UNITS ABOVE.-27 ABOVE-GRADE LEVELS, 2 BELOW-GRADE LEVELS - 422 RESIDENTIAL UNITS; Amendment; Commercial New - Revision to ApprovedArlington County · 2025
600 N Glebe Project Phase 2 - Sheeting and Shoring ONLY; Amendment; Commercial New - Revision to ApprovedArlington County · 2025$860,000
2,500 square feet or more; NA; DemolitionArlington County · 2025
Installation of new fiber dry utilities. *** PERMIT VALID FOR #1901 N MOORE ST *** **** PROPER MAINTENANCE OF TRAFFIC (MOT) PLAN MUST BE IN PLACE WHILE WORKING OR WORK WILL BE SHUT DOWN **** ***** RIGHT-OF-WAY WORK HOURS: MON-FRI 9AM-4PM; SAT-SUN 10AM-6PM ****; NA; Transportation ROW - with excavationArlington County · 2025
Permitted projects on public record. Addresses are omitted for privacy.