Installation of a new 12,000 gal fuel storage tank. We will be installing a level switch to monitor the level in the tank. Two redundant pumps will be provided to transfer product from the tank to the boiler. The entire system will be manually controlled via a local control panel mounted in the boiler room (power provided from the 240V power panel). The control panel will have a manual control switch to operate the pump when needed. The level switch will be wired to the control panel to provide an automatic shutdown of the pump and low level indication when the level switch low alarm is activated. The level switch will also provide a high level alarm indication and audible alarm horn if the tank reaches a high level during the filling operations. A secondary high level alarm indication and audible alarm horn will be mounted remotely at the tank to notify the driver filling the tank if they reach a high level alarm.City of Philadelphia · 2023
Upgrade existing residential electrical service to a 200 Amp as per 2017 necCity of Philadelphia · 2023
Install 1600 Amp Meter Bank 1 with 34 units. Install 1600 Meter Bank 2 with 33 Units. Install 800 Amp House panel. Install 600 Amp, 3-Gang, 3-phase service. Install wiring and devices throughout as per 2017 NEC. Install new fire alarm system as per 2016 NFPA 72.City of Philadelphia · 2023
Added light fixtures, receptacles, bus duct, switches, water heater, and compressor as per 2017 NEC.City of Philadelphia · 2022
1. Add 10 light fixtures
2. add 16 Receptacles
3. add 4 sensors
As per 2017 necCity of Philadelphia · 2022
New conduits and low voltage communication wire to new fuel dispensers as per 2017 nec. (A) Conduit Seals, Class I, Division 1
In Class I, Division 1 locations, conduit seals shall be located in accordance with 501.15(A)(1) through (A)(4).
This profile was built from public permit records. Claim it free to add your photo, phone, and website, so the homeowners landing here can actually reach you.
Track record sourced from public building-permit records. Figures reflect permitted projects, not self-reported work. Listed on Proven Pros.
City of Philadelphia · 2022
CHANGE OUT EXISTING 200AMP 120V-240V SINGLE PHASE PANEL WITH NEW SAME SIZE AS PER 2008 NECCity of Philadelphia · 2019
INSTALL 200 AMP/3PHASE ELECTRICAL SERVICE ON EXTERIOR WALL OF THE BUILDING FED FROM THE UTILITY POLE WITH THE PANEL INSTALLED IN THE TRAILER. INSTALLATION IS IN A NON CLASSIFIED AREA.AS PER 2008 NEC (NORTH DISTRICT)City of Philadelphia · 2018
INSTALL 70AMP/3P BREAKER IN EXISTING PANEL NEAR THE PEARLE VISION RUN 1"CONDUIT WITH #4 THWN CONDUCTORS TO A 60AMP NEMA3R DISCONNECT SWITCH WITH 50AMP FUSES LOCATED AT THE TRASH COMPACTOR.TRASH COMPACTOR PROVIDED WITH MOTOR OVERLOAD PROTECTION.AS PER 2008NEC. (SOUTH DISTRICT)City of Philadelphia · 2018
WIRE IN 4-CONTROL PANELS, FOR FAN'S, ONE FOR HEAT, WIRE IN 8-4' LIGHT FIXTURES AS PER NEC 2008City of Philadelphia · 2018
INSTALL 18 SOLAR PANELS TO HOMES EXSITING TOTAL SIZE 5.22KW PV SYSTEMCity of Philadelphia · 2018
INSTALL NEW 200AMP PANEL AND SERVICE CABLE AND REWIRE BUILDING WITH RECEPTS,SWITCHES,LIGHTS,FIXTURES,SMOKES,CO DETECTORS,PHONE,CABLE AND DOORBELL AS PER 2008 NEC (WEST DISTRICT)City of Philadelphia · 2018