adding tesla powerwall 3 and storage pack by tesla to existing solar system REV01 the original permit was to install the battery outside but client wants to have it in the garageSacramento County · 2025$30,000
installing 13.5 kw solar and two tesla powerwall 3 and new MSP. REV01 client decided not to energize his ADU unit (inlaw)section with the 2nd gateway so it was removed and both battery is connect to a gateway 200 amp for the main house REV01 client decided not to energize his ADU unit (inlaw)section with the 2nd gateway so it was removed and both battery is connect to a gateway 200 amp for the main houseSacramento County · 2025$60,000
installing 30 solar panels and two Powerwall 3 and 2 gateway 3 including the updating MSP to Eaton brand due to breaker availabilitySacramento County · 2025$61,000