MAIN CASE - Work on repairing areas under the checklist provided under the SB326, framing has Dry-rot remove all dry-rotted frame and replace with new, remove stair landing post and replace footing, paint areas that will be repaired.
This scope of work will be done to buildings, 641, 728, 700, 724, and 820. areas are located near walkway and stair landings. REV01 Removal of field welding, no welding was needed to buildings #700, #728, #724, #820 & #641, attached is the response letter from the engineer.Sacramento County · 2026$37,160
Remove and replace approximately (2,541) Sf. siding from main office, paint exterior walls and replace house-wrap paper.
Woodside HOA OffcieSacramento County · 2026$51,567
SUB CASE TO CBRC2025-00263 - Work on repairing areas under the checklist provided under the SB326, framing has Dry-rot remove all dry-rotted frame and replace with new, remove stair landing post and replace footing, paint areas that will be repaired.
This scope of work will be done to buildings, 641, 728, 700, 724, and 820. areas are located near walkway and stair landings.Sacramento County · 2026
SUB CASE TO CBRC2025-00263 - Work on repairing areas under the checklist provided under the SB326, framing has Dry-rot remove all dry-rotted frame and replace with new, remove stair landing post and replace footing, paint areas that will be repaired.
This scope of work will be done to buildings, 641, 728, 700, 724, and 820. areas are located near walkway and stair landings.Sacramento County · 2026
SUB CASE TO CBRC2025-00263 - Work on repairing areas under the checklist provided under the SB326, framing has Dry-rot remove all dry-rotted frame and replace with new, remove stair landing post and replace footing, paint areas that will be repaired.
This scope of work will be done to buildings, 641, 728, 700, 724, and 820. areas are located near walkway and stair landings.
This profile was built from public permit records. Claim it free to add your photo, phone, and website, so the homeowners landing here can actually reach you.
Track record sourced from public building-permit records. Figures reflect permitted projects, not self-reported work. Listed on Proven Pros.
Sacramento County · 2026
SUB CASE TO CBRC2025-00263 - Work on repairing areas under the checklist provided under the SB326, framing has Dry-rot remove all dry-rotted frame and replace with new, remove stair landing post and replace footing, paint areas that will be repaired.
This scope of work will be done to buildings, 641, 728, 700, 724, and 820. areas are located near walkway and stair landings.Sacramento County · 2026
UNIT 83 (645 SQ FT)
1. replace damaged portion of meta-aramid honeycomb core roof over living room with wood framed joists. Any walls supporting the new wood framed roof that are constructed of honeycomb core are to be replaced with wood wall framing.
2. replace damaged steel hoist beam with wood beam.
3. remove and reinstall undamaged utilities, like-for-like.
4. replace interior/exterior finishes, like-for-like.
UNIT 84 (645 SQ FT)
1. replace interior finishes, like-for-like.
UNIT 85 (645 SQ FT)
1. replace all meta-aramid honeycomb core roof across entire unit with wood framed joists. Any walls supporting the new wood framed roof that are constructed of honeycomb core are to be replaced with wood wall framing.
2. replace steel hoist beam with wood beam.
3. install new lateral force resisting system in wood framed walls.
4. replace damaged utilities, like-for-like.
5. replace interior/exterior finishes, like-for-like.
6. replace all damaged windows/doors.
UNIT 89 (645 SQ FT)
1. replace damaged portion of meta-aramid honeycomb core roof over bathroom/hallway/kitchen area with wood framed joists. Any walls supporting the new wood framed roof that are constructed of honeycomb core are to be replaced with wood wall framing.
2. remove and reinstall undamaged utilities, like-for-like.
3. replace interior/exterior finishes, like-for-like., CH-01 - unit 84 (645 sqft)
1. replace all meta-aramid honeycomb core ceiling/floor across entire unit with i-joists. Any walls supporting the new ceiling/floor that are constructed of honeycomb core are to be replaced with wood wall framing.
2. install new lateral force resisting system in wood framed walls.
3. remove & reinstall all undamaged electrical components (receptacles, switches, fixtures) & plumbing fixtures for framing/finish work.
4. replace interior/exterior finishes, like-for-like.
unit 83 (645 sqft)
1. update plans to reflect field changes made during city inspections. unit 84 (645 sq ft)
1. replace all meta-aramid honeycomb core ceiling/floor across entire unit with i-joists. Any walls supporting the new ceiling/floor that are constructed of honeycomb core are to be replaced with wood wall framing.
2. install new lateral force resisting system in wood framed walls.
3. remove & reinstall all undamaged electrical components (receptacles, switches, fixtures) & plumbing fixtures for framing/finish work.
4. replace interior/exterior finishes, like-for-like.
unit 83
1. update plans to reflect field changes made during city inspections.Sacramento County · 2025$200,000
Red Roof Inn
Install insulation, drywall, ductwork, exhaust fan, and paint.Sacramento County · 2025$1,500
SMUD let us know that we needed a county safety inspection to re energise the electrical panelSacramento County · 2024$100
Replace damaged interior finishes, bathroom wall framing, floor joist, subfloor, like-for-like.
Repairs to be located in the masterbathSacramento County · 2024$8,000
(Violation) Install approximately 32 square feet of 5/8" drywall (fire tape only) in lower level workshop to achieve fire separation between open crawl space and workshop.Sacramento County · 2023$350
CH-01 - unit 84 (645 sqft)
1. replace all meta-aramid honeycomb core ceiling/floor across entire unit with i-joists. Any walls supporting the new ceiling/floor that are constructed of honeycomb core are to be replaced with wood wall framing.
2. install new lateral force resisting system in wood framed walls.
3. remove & reinstall all undamaged electrical components (receptacles, switches, fixtures) & plumbing fixtures for framing/finish work.
4. replace interior/exterior finishes, like-for-like.
unit 83 (645 sqft)
1. update plans to reflect field changes made during city inspections. unit 84 (645 sq ft)
1. replace all meta-aramid honeycomb core ceiling/floor across entire unit with i-joists. Any walls supporting the new ceiling/floor that are constructed of honeycomb core are to be replaced with wood wall framing.
2. install new lateral force resisting system in wood framed walls.
3. remove & reinstall all undamaged electrical components (receptacles, switches, fixtures) & plumbing fixtures for framing/finish work.
4. replace interior/exterior finishes, like-for-like.
unit 83
1. update plans to reflect field changes made during city inspections.Sacramento County · 2022