Pavilion/Building Attached to Pavilion:
Temporary support structures for beam replacement.
Removal and replacement of up to 3 structural beams with Douglas Fir PT #1.
Dry rot repairs with knee braces and Sculptwood Max TDS for post cracks.
Reuse existing hardware, replacing fasteners as needed.
Deck Repairs (Units 117/118, 125/126, 127/128, 129/130, 131/132, 137/138, 139/140, 149/150, 157/158, 163/164, 166/165):
Lower unit decks: Remove and replace up to 4 feet of decking for upper deck footing access.
Upper unit decks: Temporary support structures installed as needed. Pour new footings 6 with 2’x2’x12” and 3 with 2’x2’x4’ footings
Install new Douglas Fir PT #1 beams, and posts,
Joist repairs (sistering only, no removal unless specified in plans).
Installation of Simpson post bases, hangers, and hurricane ties for structural reinforcement.Sacramento County · 2025
EPC - Remove and replace existing deck at back of home. Same footprint as existing.198 sq ft Carbon monoxide & Smoke alarms required. Reference CRC sections R315 & R314. “Water conserving fixtures are required to be installed throughout this residence per SB 407 (Note: Residences built after January 1, 1994 are exempt).”City of Sacramento · 2020$16,180
Permitted projects on public record. Addresses are omitted for privacy.