Install new 20kW Polar diesel generator and new 400A disconnect on existing platform; integrate existing electrical service with new generator; install new fire extinguisher in housing; install new 400A disconnect on existing H-Frame; reuse existing H-Frame; remove existing RRUs from Existing H-Frame; remove existing cabinets from platformSacramento County · 2026$30,000
Modify Existing Telecom Equip On (E) Tower - Remove Existing Valve Reg Lead-Acid Batteries And Install 8 New Ericsson 6618 Lithium-Ion BatteriesMarin County · 2025$20,000
Modification to an existing unmanned AT&T telecommunication facility consisting of: install new 30kW diesel generator with 190 gallon subbase fuel tank and level 2 acoustic enclosure on proposed 4'x10' concrete pad; integrate existing electrical service with new generator; remove existing asco panel with transfer switch; install 200A panel inside shelter; install new ATS inside shelter; install new fire extinguisher on existing shelter wall exterior; install new camlock on existing shelter wall exterior; remove existing 9'x15' concrete slab; remove obsolete metro PCS power panel and equipment., CH-01-Updated one-line diagram per Inspectors request. Updated ATS notesSacramento County · 2025$30,000
CH-01-Updated one-line diagram per Inspectors request. Updated ATS notesSacramento County · 2024
AT&T is proposing to install an emergency backup generator at an existing wireless facility. There will be no antenna/equipment changes, no frequency changes, no tower work, and no expansion of the footprint. All work for the generator installation will be completed within the existing fenced compound. The generator will only be activated during power outages and for periodic maintenance.
The scope of work for the project shall include: install a 10' x 4' concrete pad; install a 30kw generator with a 190 gallon subbase diesel fuel tank; install an automatic transfer switch and new camlock; remove and cap existing camlock; trench an underground conduit within compound for utility connections; install the Manufacturer's Acoustic Enclosure for noise shrouding.
Substantial Compliance approval requested per AB 2421.
Area served
City of Sacramento, City of Vallejo, Marin County, Sacramento County
This profile was built from public permit records. Claim it free to add your photo, phone, and website, so the homeowners landing here can actually reach you.
Track record sourced from public building-permit records. Figures reflect permitted projects, not self-reported work. Listed on Proven Pros.
Sacramento County · 2023
$30,000
Modifying existing telecommunication equipment on an existing tower site: Removal of the existing (12) valve regulated lead acid batteries from the existing battery cabinet, and replace it with (8) new lithium-ion batteries in a new B160 battery cabinet. To also remove (2) existing legacy cabinets.Sacramento County · 2026$20,000
T-Mobile Battery Replacement: Modifying existing telecommunication equipment on an existing tower site. Removal of the existing battery cabinet with the (12) Valve-Regulated Lead Acid batteries, and install (8) new lithium-ion batteries inside a new Ericsson B160 battery cabinet. No other modification to the cell siteSacramento County · 2026$20,000
EPC - T-Mobile is looking to replace the batteries within their existing cabinet with new batteries. All of the equipment locations are on ground concrete pads. The scope of work is only battery replacement within the existing cabinets, so there will be no physical changes to the look of the site.City of Sacramento · 2025$20,000
EPC - The scope of work is a battery replacement within the existing cabinet of the unmanned telecommunications site. There will be no actual changes to the physical appearance or look of the site.City of Sacramento · 2025$20,000
EPC - Replace the existing batteries within their existing cabinet with new batteries. All of the equipment locations are on ground concrete pads. The scope of work is only battery replacement within the existing cabinets, so there will be no physical changes to the look of the site.City of Sacramento · 2025$20,000
EPC - The scope of work is a battery replacement within the existing cabinets of the unmanned telecommunications site. There will be no changes to the physical appearance or look of the site.City of Sacramento · 2025$20,000
EPC - The scope of work is a battery replacement within the existing cabinets of the unmanned telecommunications site. There will be no changes to the physical appearance or look of the site.City of Sacramento · 2025$20,000